Construction cost for grey structure construction of dream house in September 2018

Its been almost an year since last time Team Overc's published grey structure construction cost 2017 article and video, response that we got on that article and video was overwhelming and encouraging that helped and guided hundreds of Pakistanis specially expatriates/overseas Pakistanis. Many other topics and issues were also addressed in form of articles and videos however grey structure cost video was the major hit both on our Youtube channel and on google rankings. 2018 has proved to be the year of change in Pakistan, things including political scenarios have completely changed which has had a great impact on economy, resulting in overall change in prices in all fields. If we talk about house construction industry, each and every material required during construction of a house witnessed an increase in prices, either it be bricks, steel, cement, tiles, wood, ceramics, labor etc. Overall construction cost of a house in 2018 has gone up by 10-12% as compared to 2017 which we will explain in this blog in form of a video as well as written article.

House construction can be done by two methods which should be known before going towards the construction cost of house:

Labor contract

A contract in which owner procures material and supervises labor on self help basis. A labor contractor is responsible for arranging required labor to carry out construction procedures. Construction cost is this case is all in hands of owner himself. Final cost of construction will depend upon how well the owner has managed construction process both in regards of material procurement and labor procurement. In this video we will discuss construction cost for this method.

Turnkey contract

This is a method or contract in which owner hires a professional company on lump sum or per square foot construction rate for a turnkey solution. Owner do not has to worry about the construction cost as the builder has agreed to provide him with all services within in predefined budget and cost. Owner only has to supervise if builder is carrying out the work as per the agreement or not. At the end of this video we will tell you how much a professional company charges for its services and how much per square foot you will have to pay extra than the cost that could have been if you build the house yourself.

Construction contract type: Labor rate contractConstruction grade: A grade compliance to all technical & engineering specifications

Sample project

10 Marla house construction cost (250 sq.yd)Covered area 3400 sq.ft including Ground floor, first floor and rooftop mumty.Item wise per square foot cost calculations

Bricks 245 Rs/sq.ft

Calculation:245 Rs x 3400 sq.ft = 833,000 RsBrick price = 9.5 Rs per pieceQuantity = 833000/9.5 = 87,684 bricks

Crush 67 Rs/sq.ft

Calculation:67 Rs x 3400 sq.ft = 227,800 RsCrush price = 78 Rs per c.ftQuantity = 227800/78 = 2,920 c.ft

Cement 195 Rs/sq.ft

Calculation:195 Rs x 3400 sq.ft = 663,000 RsCement price = 600 Rs/50kg bagQuantity = 663000/600 = 1,105 bags

Steel 202 Rs/sq.ft

Calculation:202 Rs x 3400 sq.ft = 686,800 RsSteel price = 102 Rs/kg or 102,000 Rs/tonQuantity = 686800/102 = 6,733 kg or 6.7 tons

Sand 42 Rs/sq.ft

Calculation:42 Rs x 3400 sq.ft = 142,800 RsSand price = 30 Rs/c.ftQuantity = 142800/30 = 4,760 c.ft

Labor contractor 280 Rs/sq.ft

Calculation:280 Rs x 3400 sq.ft = 952,000 Rs

Steel fixer 10 Rs/sq.ft

Calculation:10 Rs x 3400 sq.ft = 34,000 Rs

Plumbing contractor 18 Rs/sq.ft

Calculation:18 Rs x 3400 sq.ft = 61,200 Rs

Electric contractor 15 Rs/sq.ft

Calculation:18 Rs x 3400 sq.ft = 61,200 Rs

Other items

Electricity items 25 Rs/sq.ft

Calculation:25 Rs x 3400 sq.ft = 85,000 Rs

Electric items include complete uPVC conduit (pipes) required in walls, slabs, underground etc. It also includes complete switch boards internal boxes fittings required for standard Chinese fittings. Main DB (Distribution boxes) are also included in these figures for ground and first floor.

Plumbing items 50 Rs/sq.ft

Calculation:50 Rs x 3400 sq.ft = 170,000 Rs

Plumbing items include complete PPRC pipes and its fittings such as elbows, bends, T's etc required for water and gas connections. It also includes complete uPVC piping for sewerage and drain systems. It also includes a typical and standard 400 gallons plastic overhead water tank with GI (steel) pipes fitting.

Earth fill/Bharti 26 Rs/sq.ft

Calculation:26 Rs x 3400 sq.ft = 88,400 Rs

Earthfill considered in this costing is for a normal plot that is around 2 ft deep from road level and after completion of foundations till DPC requires maximum of 6ft deep earthfill. Incase of less earthfill this figure can go down.

Brick Tile 10 Rs/sq.ft

Calculation:10 Rs x 3400 sq.ft = 34,000 Rs

Brick tile is required during the process of water proofing and finishing the floor of roofs.

Guard Salary 20 Rs/sq.ft

Calculation:20 Rs x 3400 sq.ft = 68,000 Rs

Guard salary has been considered on basis of 15,000 Rs/month for a tenure of 4.5 months maximum.

Brick Ballast/Rorhi/Gravel 13 Rs/sq.ft

Calculation:13 Rs x 3400 sq.ft = 44,200 Rs

AC Copper pipe 9 Rs/sq.ft

Calculation:9 Rs x 3400 sq.ft = 30,600 Rs

It is optional and not required in most of the cases.

Bitumen 4 Rs/sq.ft

Calculation:4 Rs x 3400 sq.ft = 13,600 Rs

Polythene sheet 3 Rs/sq.ft

Calculation:3 Rs x 3400 sq.ft = 10,200 Rs

Mud 3 Rs/sq.ft

Calculation:3 Rs x 3400 sq.ft = 10,200 Rs

Chips Aggregate 4 Rs/sq.ft

Calculation:4 Rs x 3400 sq.ft = 13,600 Rs

Taxes 5 Rs/sq.ft

Calculation:5 Rs x 3400 sq.ft = 17,000 Rs

Electricity bills 5 Rs/sq.ft

Calculation:5 Rs x 3400 sq.ft = 17,000 Rs

Water boring 4 Rs/sq.ft

Calculation:4 Rs x 3400 sq.ft = 13,600 Rs

Anti termite spray 4 Rs/sq.ft

Calculation:4 Rs x 3400 sq.ft = 13,600 Rs

Random expenditures 10 Rs/sq.ft

Calculation:10 Rs x 3400 sq.ft = 34,000 Rs

Click here to understand what GREY STRUCTURE consists of and what is its PROCESS

Let us see what will be the total cost of Grey structure:

#ItemRate (Rs/sq.ft)Amount (Rs)
1Bricks245833,000
2Crush67227,800
3Cement195663,000
4Steel202686,800
5Sand42142,800
6Labor contractor280952,000
7Steel fixer1034,000
8Plumbing contractor1861,200
9Electric contractor1861,200
10Electricity items2585,000
11Plumbing items50170,000
12Earth fill/Bharti2688,400
13Brick Tile1034,000
14Guard Salary2068,000
15Brick Ballast/Rorhi/Gravel1344,200
16AC Copper pipe930,600
17Bitumen413,600
18Polythene sheet310,200
19Mud310,200
20Chips Aggregate413,600
21Taxes517,000
22Electricity bills517,000
23Water boring413,600
24Anti termite spray413,600
25Random expenditures1034,000
Total1,2694,324,800

Disclaimer:

Link to Previous 2017 Grey structure cost article.