Sudden Increase in House Construction Costs in Pakistan (2021)

2021 was a strong year for the construction sector, which witnessed a sharp upward trend after the government's real estate and construction amnesty announced in 2020. Investors and developers started various real estate and construction-related projects, and genuine buyers, particularly from overseas, took great interest in the sector, resulting in real economic activity. While this process had a positive impact on the economy overall, various challenges were also faced:

  1. A demand and supply gap was created for various construction materials
  2. Skilled labour and manpower issues were faced
  3. Scaffolding and shuttering witnessed severe shortages in the market
  4. Material prices increased

However, there were also many positives:

  1. New jobs were generated
  2. More opportunities opened up for labour and skilled personnel
  3. More activity was seen among construction material suppliers and vendors
  4. Local tile manufacturers saw more quality entrants

Getting back to the topic of the rising construction costs in 2021 — regular followers of ours will know we have been publishing yearly grey structure cost articles from 2017-2020, however a dedicated "latest grey structure cost 2021" video or article was not published, despite various requests, mainly because material prices were fluctuating on a weekly basis — it isn't possible to put together a detailed breakdown until prices settle for some time. Instead, here is a brief comparison of current grey structure cost against last year's cost. In our 2020 grey structure cost article we noted a figure of around Rs 1,400-1,450/sq.ft — currently this figure has risen to Rs 1,700-1,750/sq.ft, which is a striking 20% increase in the overall grey structure cost in the space of a few months. The cost stayed more or less the same until February-March this year — the sharp rise happened in the last few months, as key material items such as bricks, steel, cement and plumbing items all saw sharp increases. Below is an item-by-item comparison of the latest grey structure cost for 2021 against 2020.

Construction contract type: Labor rate contractConstruction grade: A grade compliance to all technical & engineering specifications

Sample project

10 Marla house construction cost (250 sq.yd)Covered area 3,400 sq.ft, including ground floor, first floor and rooftop mumty.Item wise per square foot cost calculations

Year 2020

Bricks 296 Rs/sq.ft

Calculation: 296 Rs x 3,400 sq.ft = 1,006,400 Rs — Brick price = 11.5 Rs per piece — Quantity = 87,513 bricks

Crush 67 Rs/sq.ft

Calculation: 67 Rs x 3,400 sq.ft = 227,800 Rs — Crush price = 78 Rs per c.ft — Quantity = 2,920 c.ft

Cement 175 Rs/sq.ft

Calculation: 175 Rs x 3,400 sq.ft = 595,000 Rs — Cement price = 540 Rs/50kg bag — Quantity = 1,101 bags

Steel 227 Rs/sq.ft

Calculation: 227 Rs x 3,400 sq.ft = 771,800 Rs — Steel price = 115 Rs/kg (115,000 Rs/ton) — Quantity = 6,711 kg, approx. 6.7 tons

Sand 45 Rs/sq.ft

Calculation: 45 Rs x 3,400 sq.ft = 153,000 Rs — Sand price = 32 Rs/c.ft — Quantity = 4,781 c.ft

Labor contractor 325 Rs/sq.ft

Calculation: 325 Rs x 3,400 sq.ft = 1,105,000 Rs

Steel fixer 13 Rs/sq.ft

Calculation: 13 Rs x 3,400 sq.ft = 44,200 Rs

Plumbing contractor 18 Rs/sq.ft

Calculation: 18 Rs x 3,400 sq.ft = 61,200 Rs

Electric contractor 15 Rs/sq.ft

Calculation: 15 Rs x 3,400 sq.ft = 51,000 Rs

Other items

Electricity items 35 Rs/sq.ft

Calculation: 35 Rs x 3,400 sq.ft = 119,000 Rs

Electric items include the complete uPVC conduit (pipes) required in walls, slabs and underground, along with internal switch board boxes and fittings for standard Chinese fittings, and the main distribution boxes for ground and first floor. Electric conduit saw a sharp price increase in 2019 compared to 2018.

Plumbing items 70 Rs/sq.ft

Calculation: 70 Rs x 3,400 sq.ft = 238,000 Rs

Plumbing items include complete PPRC pipes and fittings — elbows, bends, tees — required for water and gas connections, complete uPVC piping for sewerage and drain systems, and a typical 400-gallon plastic overhead water tank with GI steel pipe fittings. Plumbing conduit also saw a sharp price increase in 2019 compared to 2018.

Earth fill / Bharti 26 Rs/sq.ft

Calculation: 26 Rs x 3,400 sq.ft = 88,400 Rs

Earthfill considered here is for a normal plot around 2 ft deep from road level, which after completion of foundations up to DPC requires a maximum of 6 ft of earthfill. Where less earthfill is needed, this figure can come down.

Brick tile 12 Rs/sq.ft

Calculation: 12 Rs x 3,400 sq.ft = 40,800 Rs

Brick tile is required during water proofing and finishing of roof floors. The rate used here is up to 10 Rs per brick tile.

Guard salary 22 Rs/sq.ft

Calculation: 22 Rs x 3,400 sq.ft = 74,800 Rs

Guard salary is based on 15,000 Rs/month for a tenure of up to 5 months.

Brick ballast / Rorhi / Gravel 14 Rs/sq.ft

Calculation: 14 Rs x 3,400 sq.ft = 47,600 Rs

Bitumen 5 Rs/sq.ft

Calculation: 5 Rs x 3,400 sq.ft = 17,000 Rs

Polythene sheet 4 Rs/sq.ft

Calculation: 4 Rs x 3,400 sq.ft = 13,600 Rs

Mud 4 Rs/sq.ft

Calculation: 4 Rs x 3,400 sq.ft = 13,600 Rs

Chips aggregate 5 Rs/sq.ft

Calculation: 5 Rs x 3,400 sq.ft = 17,000 Rs

Taxes 6 Rs/sq.ft

Calculation: 6 Rs x 3,400 sq.ft = 20,400 Rs

Electricity bills 7 Rs/sq.ft

Calculation: 7 Rs x 3,400 sq.ft = 23,800 Rs

Water boring 6 Rs/sq.ft

Calculation: 6 Rs x 3,400 sq.ft = 20,400 Rs

Anti termite spray 7 Rs/sq.ft

Calculation: 7 Rs x 3,400 sq.ft = 23,800 Rs

Random expenditures 15 Rs/sq.ft

Calculation: 15 Rs x 3,400 sq.ft = 51,000 Rs

Year 2021

Bricks 360 Rs/sq.ft

Calculation: 360 Rs x 3,400 sq.ft = 1,224,000 Rs — Brick price = 14 Rs per piece — Quantity unchanged

Crush 67 Rs/sq.ft

Calculation: 67 Rs x 3,400 sq.ft = 227,800 Rs — Crush price = 78 Rs per c.ft — Quantity unchanged

Cement 220 Rs/sq.ft

Calculation: 220 Rs x 3,400 sq.ft = 748,000 Rs — Cement price = 680 Rs/50kg bag — Quantity unchanged

Steel 339 Rs/sq.ft

Calculation: 339 Rs x 3,400 sq.ft = 1,152,600 Rs — Steel price = 172 Rs/kg (172,000 Rs/ton) — Quantity unchanged

Sand 45 Rs/sq.ft

Calculation: 45 Rs x 3,400 sq.ft = 153,000 Rs — Sand price = 32 Rs/c.ft — Quantity unchanged

Labor contractor 350 Rs/sq.ft

Calculation: 350 Rs x 3,400 sq.ft = 1,190,000 Rs

Steel fixer 15 Rs/sq.ft

Calculation: 15 Rs x 3,400 sq.ft = 51,000 Rs

Plumbing contractor 20 Rs/sq.ft

Calculation: 20 Rs x 3,400 sq.ft = 68,000 Rs

Electric contractor 20 Rs/sq.ft

Calculation: 20 Rs x 3,400 sq.ft = 68,000 Rs

Other items

Electricity items 45 Rs/sq.ft

Calculation: 45 Rs x 3,400 sq.ft = 153,000 Rs

Electric conduit witnessed a sharp increase in prices in 2021 compared to 2019-20.

Plumbing items 85 Rs/sq.ft

Calculation: 85 Rs x 3,400 sq.ft = 289,000 Rs

Plumbing conduit also witnessed a sharp increase in prices in 2021 compared to 2019-20.

Earth fill / Bharti 26 Rs/sq.ft

Calculation: 26 Rs x 3,400 sq.ft = 88,400 Rs

Earthfill considered here is for a normal plot around 2 ft deep from road level, which after completion of foundations up to DPC requires a maximum of 6 ft of earthfill. Where less earthfill is needed, this figure can come down.

Brick tile 12 Rs/sq.ft

Calculation: 12 Rs x 3,400 sq.ft = 40,800 Rs

Brick tile is required during water proofing and finishing of roof floors. The rate used here is up to 10 Rs per brick tile.

Guard salary 25 Rs/sq.ft

Calculation: 25 Rs x 3,400 sq.ft = 85,000 Rs

Guard salary is based on 17,000 Rs/month for a tenure of up to 5 months.

Brick ballast / Rorhi / Gravel 14 Rs/sq.ft

Calculation: 14 Rs x 3,400 sq.ft = 47,600 Rs

Bitumen 5 Rs/sq.ft

Calculation: 5 Rs x 3,400 sq.ft = 17,000 Rs

Polythene sheet 5 Rs/sq.ft

Calculation: 5 Rs x 3,400 sq.ft = 17,000 Rs

Mud 4 Rs/sq.ft

Calculation: 4 Rs x 3,400 sq.ft = 13,600 Rs

Chips aggregate 5 Rs/sq.ft

Calculation: 5 Rs x 3,400 sq.ft = 17,000 Rs

Taxes 6 Rs/sq.ft

Calculation: 6 Rs x 3,400 sq.ft = 20,400 Rs

Electricity bills 10 Rs/sq.ft

Calculation: 10 Rs x 3,400 sq.ft = 34,000 Rs

Water boring 6 Rs/sq.ft

Calculation: 6 Rs x 3,400 sq.ft = 20,400 Rs

Anti termite spray 15 Rs/sq.ft

Calculation: 15 Rs x 3,400 sq.ft = 51,000 Rs

Random expenditures 20 Rs/sq.ft

Calculation: 20 Rs x 3,400 sq.ft = 68,000 Rs

#Item2020 (Rs/sq.ft)2021 (Rs/sq.ft)
1Bricks296360
2Crush6767
3Cement175220
4Steel227339
5Sand4545
6Labor contractor325350
7Steel fixer1315
8Plumbing contractor1820
9Electric contractor1520
10Electricity items3545
11Plumbing items7085
12Earth fill / Bharti2626
13Brick tile1212
14Guard salary2225
15Brick ballast / Rorhi / Gravel1414
16Bitumen55
17Polythene sheet45
18Mud44
19Chips aggregate55
20Taxes66
21Electricity bills710
22Water boring66
23Anti termite spray715
24Random expenditures1520
Total1,4191,719