Construction cost for grey structure construction of dream house
After discussing size and location of plot in previous episode, in this video we will discuss about construction cost. Costing and budgeting for house construction before starting the project is very important task to carry operations smoothly. One should have the basic idea about construction cost which can be helpful in making a roadmap for construction specially if onehttps://web.archive.org/web/20210423132533/https://www.youtube.com/watch?v=1rkhmfDd1eI has budget constraints. Our team has calculated estimated per square foot costs for different materials required during grey structure construction of a house.
1 Kanal contemporary structure by Team Overc’s in Bahria town Lahore
House construction can be done by two methods which should be known before going towards the construction cost of house:
Labor contract
A contract in which owner procures material and supervises labor on self help basis. A labor contractor is responsible for arranging required labor to carry out construction procedures. Construction cost is this case is all in hands of owner himself. Final cost of construction will depend upon how well the owner has managed construction process both in regards of material procurement and labor procurement. In this video we will discuss construction cost for this method.
–
–
–
Turnkey contract
1 Kanal contemporary structure by Team Overc’s in Bahria town Lahore
This is a method or contract in which owner hires a professional company on lump sum or per square foot construction rate for a turnkey solution. Owner do not has to worry about the construction cost as the builder has agreed to provide him with all services within in predefined budget and cost. Owner only has to supervise if builder is carrying out the work as per the agreement or not. At the end of this video we will tell you how much a professional company charges for its services and how much per square foot you will have to pay extra than the cost that could have been if you build the house yourself.
Construction contract type: Labor rate contract
Construction grade: A grade compliance to all technical & engineering specifications
Sample project
10 Marla house construction cost (250 sq.yd)
Covered area 3400 sq.ft
Item wise per square foot cost calculations
Bricks 220 Rs/sq.ft
Calculation:
220 Rs x 3400 sq.ft=748000 Rs
Brick price =8.5 Rs per piece
Quantity =748000/8.5 = 88000 bricks
Crush 60 Rs/sq.ft
Calculation:
60 Rs x 3400 sq.ft=204000 Rs
Crush price =70 Rs per c.ft
Quantity =204000/70 = 2915 c.ft
Cement 175 Rs/sq.ft
Calculation:
175 Rs x 3400 sq.ft=595000 Rs
Cement price =550 Rs/50kg bag
Quantity =595000/550 = 1082 bags
Steel 175 Rs/sq.ft
Calculation:
175 Rs x 3400 sq.ft=595000 Rs
Steel price =80 Rs/kg or 80000R s/ton
Quantity =595000/80 = 7437 kg or 7.4 tons
Sand 35 Rs/sq.ft
Calculation:
35 Rs x 3400 sq.ft=119000 Rs
Sand price =25 Rs/c.ft
Quantity =119000/25 = 4760 c.ft
Labor contractor 260 Rs/sq.ft
Calculation:
260 Rs x 3400 sq.ft = 884000 Rs
Steel fixer 10 Rs/sq.ft
Calculation:
10 Rs x 3400 sq.ft = 34000 Rs
Plumbing contractor 15 Rs/sq.ft
Calculation:
15 Rs x 3400 sq.ft = 51000 Rs
Electric contractor 15 Rs/sq.ft
Calculation:
15 Rs x 3400 sq.ft = 51000 Rs
Other items
Electricity items 20 Rs/sq.ft
Calculation:
20 Rs x 3400 sq.ft= 68000 Rs
Plumbing items 45 Rs/sq.ft
Calculation:
45 Rs x 3400 sq.ft= 153000 Rs
Earth fill/Bharti 26 Rs/sq.ft
Calculation:
26 Rs x 3400 sq.ft= 88400 Rs
Brick Tile 10 Rs/sq.ft
Calculation:
10 Rs x 3400 sq.ft= 34000 Rs
Guard Salary 20 Rs/sq.ft
Calculation:
20 Rs x 3400 sq.ft= 68000 Rs
Brick Ballast/Rorhi/Gravel 13 Rs/sq.ft
Calculation:
13 Rs x 3400 sq.ft= 44200 Rs
AC Copper pipe 9 Rs/sq.ft
Calculation:
9 Rs x 3400 sq.ft= 30600 Rs
Bitumen 4 Rs/sq.ft
Calculation:
4 Rs x 3400 sq.ft= 13600 Rs
Electricity items 20 Rs/sq.ft
Calculation:
20 Rs x 3400 sq.ft= 68000 Rs
Polythene sheet 3 Rs/sq.ft
Calculation:
3 Rs x 3400 sq.ft= 10200 Rs
Mud 3 Rs/sq.ft
Calculation:
3 Rs x 3400 sq.ft= 10200 Rs
Chips Aggregate 4 Rs/sq.ft
Calculation:
4 Rs x 3400 sq.ft= 13600 Rs
Taxes 5 Rs/sq.ft
Calculation:
5 Rs x 3400 sq.ft= 17000 Rs
Electricity bills 5 Rs/sq.ft
Calculation:
5 Rs x 3400 sq.ft= 17000 Rs
Water boring 4 Rs/sq.ft
Calculation:
4 Rs x 3400 sq.ft= 13600 Rs
Anti termite spray 4 Rs/sq.ft
Calculation:
4 Rs x 3400 sq.ft= 13600 Rs
Random expenditures 10 Rs/sq.ft
Calculation:
10 Rs x 3400 sq.ft= 34000 Rs
Let us see what will be the total cost of Grey structure:
S# | Item | Cost per sq.ft | Total approximate price(Pak Rs) |
1 | Bricks | 220 | 748000 |
2 | Crush | 60 | 204000 |
3 | Cement | 175 | 595000 |
4 | Steel | 175 | 595000 |
5 | Sand | 35 | 119000 |
6 | Labor Cont | 260 | 884000 |
7 | Steel fixer | 10 | 34000 |
8 | Plumbing | 15 | 51000 |
9 | Electric | 15 | 51000 |
10 | Electric items | 20 | 68000 |
11 | Plumbing items | 45 | 153000 |
12 | Earth fill | 26 | 88400 |
13 | Brick tile | 10 | 34000 |
14 | Guard salary | 20 | 68000 |
15 | Brick ballast | 13 | 44200 |
16 | AC pipe | 9 | 30600 |
17 | Bitumen | 4 | 13600 |
18 | Polythene sheet | 3 | 10200 |
19 | Mud | 3 | 10200 |
20 | Chips | 4 | 13600 |
21 | Taxes | 5 | 17000 |
22 | Electric bills | 5 | 17000 |
23 | Boring | 4 | 13600 |
24 | Anti termite | 4 | 13600 |
25 | Random | 10 | 34000 |
__ | TOTAL COST | 1150 | 3,910,000 |
In case your house is not 10 marla:
House size (marla) | Usual Covered Areas(sq.ft) | Total cost (Pak Rs) |
8 | 2900 | 3,335,000 |
12 | 3600 | 4,140,000 |
20 | 5300 | 6,095,000 |
Disclaimer:
-Possible ±5% Variation is possible in cost shown in video
-Rates applicable on Brick structures only
-Add Rs 100-150 for frame structure construction
-Skills required to achieve this cost:
-Past construction experience
-Quality & honest labor
-Labor management skills
-Quality, timely & cost effective material procurement
-Factors such as construction inexperience, unusual
covered areas, frequent wear & tears, fraudulent labor
etc can effect this cost figure
-Hire professional company which will add a figure of 150 Rs/sq.ft
maximum as margin.
-Basement grey structure will cost minimum 1800 Rs/sq.ft (Basement costing article can be found in blogs section)