Team Overcs

Cost for Grey structure house construction

Dec 2019 UPDATE: Rates of certain materials have increased hence overall per square foot cost has gone up. Latest video has been posted and click here to go to latest house construction grey structure cost article.

Aug 2018 UPDATE: Rates of certain materials have increased hence overall per square foot cost has gone up. Latest video has been posted and click here to go to latest house construction grey structure cost article.

Construction cost for grey structure construction of dream house

After discussing size and location of plot in previous episode, in this video we will discuss about construction cost. Costing and budgeting for house construction before starting the project is very important task to carry operations smoothly. One should have the basic idea about construction cost which can be helpful in making a roadmap for construction specially if onehttps://web.archive.org/web/20210423132533/https://www.youtube.com/watch?v=1rkhmfDd1eI has budget constraints. Our team has calculated estimated per square foot costs for different materials required during grey structure construction of a house.

1 Kanal contemporary structure by Team Overc’s in Bahria town Lahore

House construction can be done by two methods which should be known before going towards the construction cost of house:

Labor contract

A contract in which owner procures material and supervises labor on self help basis. A labor contractor is responsible for arranging required labor to carry out construction procedures. Construction cost is this case is all in hands of owner himself. Final cost of construction will depend upon how well the owner has managed construction process both in regards of material procurement and labor procurement. In this video we will discuss construction cost for this method.

 Turnkey contract

1 Kanal contemporary structure by Team Overc’s in Bahria town Lahore

This is a method or contract in which owner hires a professional company on lump sum or per square foot construction rate for a turnkey solution. Owner do not has to worry about the construction cost as the builder has agreed to provide him with all services within in predefined budget and cost. Owner only has to supervise if builder is carrying out the work as per the agreement or not. At the end of this video we will tell you how much a professional company charges for its services and how much per square foot you will have to pay extra than the cost that could have been if you build the house yourself.

 

 

Construction contract type: Labor rate contract

Construction grade: A grade compliance to all technical & engineering specifications

 

Sample project

10 Marla house construction cost (250 sq.yd)

Covered area 3400 sq.ft

Item wise per square foot cost calculations

Bricks 220 Rs/sq.ft

Calculation:

220 Rs x 3400 sq.ft=748000 Rs

Brick price           =8.5 Rs per piece

Quantity              =748000/8.5 = 88000 bricks

Crush 60 Rs/sq.ft

Calculation:

60 Rs x 3400 sq.ft=204000 Rs

Crush price       =70 Rs per c.ft

Quantity         =204000/70 = 2915 c.ft

Cement 175 Rs/sq.ft

Calculation:

175 Rs x 3400 sq.ft=595000 Rs

Cement price       =550 Rs/50kg bag

Quantity              =595000/550 = 1082 bags

Steel 175 Rs/sq.ft

Calculation:

175 Rs x 3400 sq.ft=595000 Rs

Steel price             =80 Rs/kg or 80000R s/ton

Quantity              =595000/80 = 7437 kg or 7.4 tons

Sand 35 Rs/sq.ft

Calculation:

35 Rs x 3400 sq.ft=119000 Rs

Sand price         =25 Rs/c.ft

Quantity             =119000/25 = 4760 c.ft

Labor contractor 260 Rs/sq.ft

Calculation:

260 Rs x 3400 sq.ft = 884000 Rs

Steel fixer 10 Rs/sq.ft

Calculation:

10 Rs x 3400 sq.ft = 34000 Rs

Plumbing contractor 15 Rs/sq.ft

Calculation:

15 Rs x 3400 sq.ft = 51000 Rs

Electric contractor 15 Rs/sq.ft

Calculation:

15 Rs x 3400 sq.ft = 51000 Rs

Other items

Electricity items 20 Rs/sq.ft

Calculation:

20 Rs x 3400 sq.ft= 68000 Rs

Plumbing items 45 Rs/sq.ft

Calculation:

45 Rs x 3400 sq.ft= 153000 Rs

Earth fill/Bharti 26 Rs/sq.ft

Calculation:

26 Rs x 3400 sq.ft= 88400 Rs

Brick Tile 10 Rs/sq.ft

Calculation:

10 Rs x 3400 sq.ft= 34000 Rs

Guard Salary 20 Rs/sq.ft

Calculation:

20 Rs x 3400 sq.ft= 68000 Rs

Brick Ballast/Rorhi/Gravel 13 Rs/sq.ft

Calculation:

13 Rs x 3400 sq.ft= 44200 Rs

AC Copper pipe 9 Rs/sq.ft

Calculation:

9 Rs x 3400 sq.ft= 30600 Rs

Bitumen 4 Rs/sq.ft

Calculation:

4 Rs x 3400 sq.ft= 13600 Rs

Electricity items 20 Rs/sq.ft

Calculation:

20 Rs x 3400 sq.ft= 68000 Rs

Polythene sheet 3 Rs/sq.ft

Calculation:

3 Rs x 3400 sq.ft= 10200 Rs

Mud 3 Rs/sq.ft

Calculation:

3 Rs x 3400 sq.ft= 10200 Rs

Chips Aggregate 4 Rs/sq.ft

Calculation:

4 Rs x 3400 sq.ft= 13600 Rs

Taxes 5 Rs/sq.ft

Calculation:

5 Rs x 3400 sq.ft= 17000 Rs

Electricity bills 5 Rs/sq.ft

Calculation:

5 Rs x 3400 sq.ft= 17000 Rs

Water boring 4 Rs/sq.ft

Calculation:

4 Rs x 3400 sq.ft= 13600 Rs

Anti termite spray 4 Rs/sq.ft

Calculation:

4 Rs x 3400 sq.ft= 13600 Rs

Random expenditures 10 Rs/sq.ft

Calculation:

10 Rs x 3400 sq.ft= 34000 Rs

Let us see what will be the total cost of Grey structure:

S# Item Cost per sq.ft Total approximate price(Pak Rs)
1 Bricks 220 748000
2 Crush 60 204000
3 Cement 175 595000
4 Steel 175 595000
5 Sand 35 119000
6 Labor Cont 260 884000
7 Steel fixer 10 34000
8 Plumbing 15 51000
9 Electric 15 51000
10 Electric items 20 68000
11 Plumbing items 45 153000
12 Earth fill 26 88400
13 Brick tile 10 34000
14 Guard salary 20 68000
15 Brick ballast 13 44200
16 AC pipe 9 30600
17 Bitumen 4 13600
18 Polythene sheet 3 10200
19 Mud 3 10200
20 Chips 4 13600
21 Taxes 5 17000
22 Electric bills 5 17000
23 Boring 4 13600
24 Anti termite 4 13600
25 Random 10 34000
 
__ TOTAL COST 1150 3,910,000

 

In case your house is not 10 marla:

 

House size (marla) Usual Covered Areas(sq.ft) Total cost (Pak Rs)
8 2900 3,335,000
12 3600 4,140,000
20 5300 6,095,000

Disclaimer:

-Possible ±5% Variation is possible in cost shown in video
-Rates applicable on Brick structures only
-Add Rs 100-150 for frame structure construction
-Skills required to achieve this cost:
-Past construction experience
-Quality & honest labor
-Labor management skills
-Quality, timely & cost effective material procurement
-Factors such as construction inexperience, unusual
covered areas, frequent wear & tears, fraudulent labor
etc can effect this cost figure
-Hire professional company which will add a figure of 150 Rs/sq.ft
maximum as margin.
-Basement grey structure will cost minimum 1800 Rs/sq.ft (Basement costing article can be found in blogs section)

Aug 2018 UPDATE: Rates of certain materials have increased hence overall per square foot cost has gone up. Latest video has been posted and click here to go to latest house construction grey structure cost article.

Leave a Reply

Your email address will not be published. Required fields are marked *